Trading with a commitment to quality since 1980.

Equatic Civil Engineering and Water Management

A range of projects working within water courses across Lancashire. 

Creation of a Fish Pass

Houghton Bottoms - River Darwen


We carried out the construction of a fish easement in the form of a rock ramp at Houghton Bottoms Weir on the River Darwen.
The weir is a high vertical horse-shoe stone weir with an irregular bedrock outcrop on the left side. This was a complete barrier to the migration of fish.
We constructed a fish pass by building a retaining wall up the bedrock outcrop along the left of the weir, and between the new wall and the existing channel wall we constructed an embedded rock-ramp enabling fish to swim up and over the weir. 
The rock ramp was finished with a rough surface creating a turbulent flow. 
It included a central low-flow channel to enable fish passage in low flow conditions.
This was a highly sensitive project with regards to the environment. 
In order to eliminate all risks, planning was carried out to great depths and procedures put in place to eliminate all risks, working to the environment agency’s agreed method statement and permit.
We constructed a coffer dam in order to carry out the works. Rapid set concrete was used to reduce risks of leaching. 

Samlesbury Weir Removal 

Samlesbury - River Ribble


Removal of a redundant gauging weir on the River Ribble at Samlesbury. The weir was a concrete flat V type weir with two baffle walls, with the downstream weir face finishing with a vertical face at the apron. On the right-hand bank there was a stilling well and land drainage outlet, the stilling well was filled and capped. Works were completed from left hand bank to reduce ground disturbance to Brockholes Nature Reserve site. The banks immediately adjacent to the site were reprofiled after the removal of the weir in keeping with the natural gradient of surrounding banks. The left-hand bank was reprofiled 100m up from the removed structure to reinstate riverbank and mitigate erosion potential from water level reductions. Through this project, we salvaged and recycled the arisings from the concrete weir and crushed it off-site to create recycled 6F2 sub-base material that was used on various other projects. 

Holland Wood Weir

Walton-le-dale - River Darwen


The works were to construct a fish pass on the River Darwen. 
This project delivered a  fish pass solution and commenced the programme of returning anadromous fish and catadromous fish to the River Darwen. The sloped faced weir constructed of concrete is over 3m high and was constructed to feed a mill. A new river channel was constructed in the grassland on the north side of the weir and around 10% of flow was redirected, bypassing the weir and allowing migrating fish to access the river upstream.

Pincroft Weir 

Adlington, Chorley - River Douglas


This project was the construction and formation of a fish pass solution. Pincroft Weir is a low-head weir located on the River Douglas downstream of the Pincroft Dyeworks in Adlington. The weir was acting as a barrier to fish migration especially in low flows. The works were to create a rock ramp fish easement with a low flow channel to address the partial barrier to fish migration. The rock ramp was formed using various sized boulders and stone bedded into concrete. 


Grimeford Lane Weir


Adlington, Chorley - River Douglas



Formation of a loose fill rock ramp created using various sizes boulders with a low flow channel to address the fish migration issue. The weir was considered to be acting as a partial barrier to fish migration at low water levels. Temporary works were installed at commencement; sand bags and visqueen to halt the flow of water into the working area and a silt curtain to reduce the risk of sediment flowing into the water course








Share by: